Case Study 1 - GMJV: Bothwell Bank PDF Print

Turnkey Solution - Design, Manufacture, Installation and Commissioning of Primary Settlement Tank (PST) Scrapers

Download this Case Study

* Cost effective refurbishment of old sewage treatment equipment

* Improved operational performance of primary settlement tanks

* Bespoke and tailored solution to meet our customer’s specific requirements

Problem :                                                                                              Image

Two primary settlement tank scrapers operated by Scottish Water had fallen into disrepair and were causing a hold up of sludge within the tanks leading to diminishing performance with a subsequent effect on the downstream processes.

The main problem with both of the scrapers was the collapsed scum skimming arrangement which was supported peripherally by the scum board.

Solution :

Scottish Water needed to replace the scrapers and since existing supplier framework agreements had expired a contract was awarded to GMJV who sourced tenders from the marketplace for the refurbishment of the scrapers. 

Xm Services became involved in the tendering process and initially performed a series of site visits to understand the scope of the project requirements which essentially involved the decommissioning and removal of the existing scrapers and the design, manufacture, supply, installation and commissioning of two replacements, all within a five month period.

Image

Using its global network of wastewater equipment suppliers supported by its local engineering expertise, Xm Services was able to identify and create the most cost effective bespoke turnkey solution, delivering the required operational benefits in terms of robustness and within the specified time frame.

Following the submission of its proposal, Xm Services was formally interviewed and audited by GMJV to demonstrate the procedures it uses to monitor and control health and safety issues and also to present the quality system in place used as a part of ISO9001:2000 accreditation.

 

Being successful at this stage, GMJV awarded the turnkey contract to Xm Services for the refurbishment of the two scrapers which comprised the following:

Effective project management through rigorous implementation of the ISO9001:2000 quality systems.

Image

Preparation of detailed design documentation including:, full site surveys, functional design specification, general assembly drawings, component drawings, load calculations, design risk assessments, method statements, design review meetings and approval documentation.

Overseeing the manufacture of the equipment and performing the necessary Factory Acceptance Tests (FAT) and inspections prior to the equipment being despatched to the UK to ensure conformity with EC standards and the agreed design specification.

Coordination of the equipment delivery with the emptying of the settlement tanks to minimise disruption to the operation of the sewage plant.

Provision of all refurbishment activities including: site supervision, confined space qualified personnel, qualified first aiders, all necessary tools and equipment, cranage, scrap disposal, mechanical and electrical assembly and installation, completion of NICEIC certification and Site Acceptance Tests (SAT).

Provision of training during handover and submission of as-built documentation.

Benefits :

The design of the scrapers was modified so that the scum skimmer arrangement was mounted from the scraper arm and not by peripheral rollers, which improved its robustness and led to a cost saving.

"GMJV had an opportunity to test the market by seeking like-for-like equipment replacement or an alternative design offering a cost saving. Xm Services responded quickly at short notice and provided a design that met the client s needs at significantly lower cost"
"We were satisfied with our checks and Xm provided an efficient and flexible service throughout the design and installation phases, working with us to overcome site constraints, delivering on time and to budget. We would be happy to consider them for future projects"
DOUG FOWLER, Project Manager, GMJV
 
Main Menu
Xm Services
Xm Services News
Virtual Brochure
Useful Links
Advanced Search
Contact Xm Services
Xm News
 
 

Xm Services, Baldovie Road, Dundee, Angus, Scotland, DD4 8UQ

Powered by Total Ecommerce
Xm Services